施工技術(shù)總結(jié)
一、工程概況
千禧鵲橋、田園橋、花橋、余慶橋、萬(wàn)壽龜橋及增加的引橋,是水上街市吉慶廣場(chǎng)工程的組成部分,是聯(lián)系各境點(diǎn)及各境區(qū)之間的走廊。由深圳市海上田園風(fēng)光旅游開(kāi)發(fā)公司興建、東南大學(xué)建筑設(shè)計(jì)院設(shè)計(jì)、寶安監(jiān)理公司監(jiān)理、深圳市華僑建筑工程公司承建施工。橋身主體為鋼筋混凝土結(jié)構(gòu),基礎(chǔ)以φ550水泥攪拌樁為支承點(diǎn)在上設(shè)獨(dú)立條型鋼筋砼承臺(tái),橋高4.8m,橋長(zhǎng)分別7m~12m,寬度m3.6~12m,五座橋總工程造價(jià)為136萬(wàn)元。
本五座橋工程于2001年9月10日相繼開(kāi)工,并于2001年12月5日全部完工,歷時(shí)95天,工程質(zhì)量達(dá)到優(yōu)良。
二、施工管理及組織
我公司根據(jù)業(yè)主的使用要求,本著以主人翁的精神,以目標(biāo)統(tǒng)攬全局,以經(jīng)濟(jì)承包為杠桿進(jìn)行精心組織、科學(xué)管理,建立一個(gè)權(quán)限明確、責(zé)任清晰、分項(xiàng)細(xì)致、要求嚴(yán)格、高效率的管理組織機(jī)構(gòu)和素質(zhì)過(guò)硬的專(zhuān)業(yè)施工隊(duì)伍,其形式和投入的主要人員及機(jī)械設(shè)備如下:
1、管理形式
Construction Technology
First, project survey
Millennium bridge of magpies, garden bridge, Huaqiao, Yuqing Bridge, Wanshou turtle bridge and increase bridge, water markets are an integral part of Kat Hing Square project is the contact point of the border and the border areas between the corridors. Rural scenery sea from Shenzhen Municipal Tourism Development Company to build, Southeast University Design Institute Building, Baoan Management Project Management Company, Shenzhen Overseas Chinese construction company contracted the construction. The main deck of reinforced concrete structures, cement treated base to φ550 supporting point for the independent bar in the design of reinforced concrete caps, bridge high 4.8m, bridge lengths of 7m ~ 12m, width m3.6 ~ 12m, five bridges The total project cost is 1.36 million yuan.
The five bridges project in September 10, 2001 have been started, and in December 5, 2001 completed and lasted 95 days, quality is excellent.
Second, construction management and organization
Our requirements under the owner's use, in line with the spirit masters, to target the overall situation, to contract as a lever for economic well-organized, scientific management, the establishment of a clear authority and responsibility clear, detailed breakdown, demanding, high-efficiency management organization and the quality of excellent professional construction team, in the form and input of key personnel and mechanical equipment are as follows:
1, form of management