管樁施工方案.doc
進入下載頁
第一節 工程概況
一、工程簡介
擬建的實驗樓,位于C市J區,五層現澆鋼筋砼框架結構,總建筑面積約9008平方米;采用D400管樁承臺基礎,無地下室,瓦屋面(坡屋面);
工期:暫定于2005年×月×日開工,于2005年×月×日竣工,總工期為147個日歷天
現場條件:本工程的施工場地已平整,施工提供用水總管徑為DN250mm,施工用電提供總負荷為200KW;施工范圍內可通行施工車輛及供施工設備和材料小量分批堆放。
工程施工范圍:包括紅線范圍內的土建工程、水電安裝工程、裝修工程施工。具體專業內容包括建筑、結構、給排水系統、電氣工程(包括防雷工程)、消防和噴淋系統、空調系統、裝修工程、人防工程等。
質量標準:達到《工程施工質量驗收規范》合格標準,爭創優良工程。工程竣工驗收達不到合同約定的質量標準的,我公司向發包人交納審定結算總價2%的違約金。
保修期限:按中華人民共和國國務院令第279號《建設工程質量管理條例》和建設部2000年第80號令的規定執行。保修期自竣工驗收簽字之日起計。
竣工資料:確定工程竣工時間前14天內,我公司向招標人(由監理單位先行審查合格)提交符合建檔管理規定要求的竣工資料一式肆份。
二、建筑工程
Section Project Profiles
I. Brief Introduction of
The proposed laboratory building, located at C City, J District, five-situ reinforced concrete frame structure with a total construction area of about 9008 square meters; with D400 pile cap foundation, no basement, tile roof (sloping roof);
Duration: tentatively scheduled for 2005 × month × day started at 2005 × month × date completed, the total duration of 147 calendar days
Field conditions: the project's construction site has been formed, the total diameter of the construction to provide water DN250mm, construction of electricity to provide the total load of 200KW; construction within the scope of access for construction vehicles and construction equipment and materials piling up small batches.
Construction area: including the red line within the scope of civil engineering, water and electricity installation, renovation construction. Specific expertise includes architecture, structure, drainage systems, electrical works (including mine works), fire and sprinkler systems, air-conditioning system, renovation, civil air defense projects.
Quality Standard: meet, "Construction Quality Acceptance of" eligibility criteria, striving to good works. Projects reach completion and acceptance of quality standards agreed in the contract, the company paid to the developer is audited balance sheet total of 2% penalty.
Warranty period: According to The People's Republic of China State Council Order No. 279, "Construction Quality Control Regulations" and the Ministry of Construction Decree 80 of 2000 shall apply. Warranty period from signing the final acceptance date.
Completion data: identification work is completed within 14 days prior to the time, my company to the tenderer (first pass the examination by the supervisory agencies) to the regulations meet the filing requirements of the completion data of a type wantonly copies.
Second, construction