1、 攪拌機應設置在平坦的位置,用方木墊起前后輪軸,使輪胎擱高架空,以免在開動時發生走動。
2、 攪拌機應實施二級漏電保護,上班前電源接通后,必須仔細檢查,經空車試轉認為合格,方可使用。試運轉時應校驗拌筒轉速是否合適,一般情況下,空車速度比重車(裝料后)稍快2-3轉,如相差較多,應調整動輪與傳動輪的比例。
3、 拌筒的旋轉方向應符合箭頭指示方向,如不符時,應更正電機接線。
4、 檢查傳動離合器和制動器是否靈活可靠,鋼絲繩有無損壞,軌道滑輪是否良好,周圍有無障礙及各部件的潤滑情況等。
5、 開機后,經常注意攪拌機各部件的運轉是否正常。停機時。經常檢查攪拌機葉片是否打彎、螺絲有否打落或松動。
6、 當混凝土攪拌完畢或預計停歇1小時以上,除將余料出凈外,應用石子和清水倒入拌筒內,開機轉動,把粘在料筒上的砂漿沖洗干凈后全部卸出。料筒內不得有積水,以免料筒和葉片生銹。同時還應清理攪拌筒外積灰,使機械保持清潔完好。
7、 下班后及停機不用時,將保險絲取下,以策安全。
8、嚴禁操作人員在酒后進入施工現場作業。
9、每個工人進入施工現場都必須頭戴安全帽。
10、班組如果因勞力不足需要再招新工人時,應事先向工地報告。
11、新工人進場后應先經過三級安全交底,并經考試合格后方可讓其正式上崗。
12、新工人進場應具有四證,即:職業資質證、身份
Abstract:
1, mixer should be set in the flat position, with a square wooden paving the front and rear wheels, put the tires of high overhead, in order to avoid walking when starting.
2, mixer should implement two leakage protection, before work, after power on, must be carefully examined by the empty test switch that qualified before use. Commissioning should check the suitability of mixing barrel speed, under normal circumstances, the proportion of empty vehicle speed (after loading) 2-3 faster transfer, such as the difference between the more and the drive wheels should be adjusted to the ratio of wheel.
3, mixing drum rotation direction should be consistent with direction of the arrow, such as discrepancies should be correct electrical wiring.
4, check whether the drive clutch and brake flexible and reliable, wire rope for damage, track wheels are good and the parts around the barrier-free lubrication and so on.
5, is turned on, always pay attention to all parts of the mixer is functioning properly. Shutdown. Regular checks of mixer blade is bent, has knocked out or loose screws.
6, when the concrete mixing is completed or is expected to rest 1 hour more than I expected out of the net, the application of gravel and water into the mixing tube, and start turning to the mortar stuck to clean the barrel after all the unloading. The barrel may not have stagnant water and leaf rust barrel. Should also clean up outside the mixing tube fouling, so that the machinery clean intact.
7, after work and shut down when not in use, remove the fuse for safety.
8, non-operators in the drink to the construction site work.
9, each worker entering the construction site must be wearing helmets.
10 team if the need to move because of a labor shortage of new workers, the report shall be submitted to the site.
11, after the admission of new workers should go through three security correspondent, and pass the examination before they can let the official posts.
12, the new approach should have four cards of workers, namely: professional qualification certificate, identity