一、 施工準備
(一) 作業條件
1、 人工成孔樁孔,井壁支護要根據該地區的土質特點、地下水分布情況,編制切實可行的施工方案,迸行井壁支護的計算和設計。
2、 開挖前場地完成三通一平。地上、地下的電纜、管線、舊建筑物、設備基礎等障礙物均已排除處理完畢。各項臨時設施,如照明、動力、通風、安全設施準備就緒。
3、 熟悉施工圖紙及場地的地下土質、水文地質資料,做到心中有數。
4、 按基礎平面圖,設置樁位軸線、定位點;樁孔四周灑灰線,測定高程水準點。放線工序完成后,辦理驗收手續。
5、 按設計要求分段做好鋼筋籠。
6、 全面開挖之前,有選擇地先挖兩個試驗樁孔,分析土質、水文等有關情況,以此修改原編施工方案。
7、 在地下水位比較高的區域,先降低地下水位至樁底以下0.5m左右。
8、 人工挖孔操作的安全至關重要,開挖前對施工人員進行全面的安全技術交底;操作前對吊具進行安全可靠的檢查和試驗,確保施工安全。
(二) 材料要求
1、 水泥:采用32.5級以上普通硅酸鹽水泥
First, construction preparation
(A) Operating conditions
1, artificial into the pile hole, retaining wall according to the characteristics of the region's soil, water distribution, preparation of practical construction program, borehole into line calculation and design support.
2, before the excavation site to complete leveling. Ground, underground cables, pipes, old buildings, equipment and other obstructions have been excluded based processed. The temporary facilities, such as lighting, power, ventilation, safety equipment ready.
3, familiar with the construction drawings and site of the underground soil, hydrogeology information, be aware of.
4, according to foundation plan, set the pile-bit axes, positioning points; Piles gray line around the spill to determine the standard point of elevation. Actinomyces process is complete, go through inspection procedures.
5, according to design requirements sub good reinforcement cage.
6, prior to full excavation, selected first hole dug two test piles, analysis of soil, hydrology and other relevant information in order to modify the original code construction scheme.
7, in the relatively high water table areas, first reduce the water table to pile the following about 0.5m.
8, manual digging operation is of utmost importance, before excavation of the safety of construction workers to conduct a comprehensive classification of components; operation before the spreader for safe and reliable inspection and testing, to ensure construction safety.
(B) material requirements
1 cement: The more than ordinary portland cement 32.5