一、 施工準備
(一) 鋼筋工程
1、 作業條件
(1) 鋼筋綁扎前,核對鋼筋加工料表是否正確,并檢查有無銹蝕現象,除銹后再運至施工部位。
(2) 做好放線工作J單出柱、墻的位置線,并彈好鋼筋位置線。
2、 材料要求
(1) 鋼筋:級別、規格符合設計要求。質量符合現行標準要求。
(2) 20~22#火燒絲、水泥砂漿(塑料)墊塊等。
3、 機具準備
(1) 鋼筋切斷機、鋼筋彎曲機、鋼筋調直機、鋼筋鉤子、鋼筋扳子、鋼絲刷、斷火燒絲鍘刀等。
(2) 墨斗、墨汁、小白線、粉筆等。
(二) 模板工程
1、 作業條件
(1) 外墻高出300mm部分模板采用竹膠板拼
First, construction preparation
(A) of the steel works
1, operating conditions
(1) steel banding before the check sheet steel processing material is correct and check for corrosion phenomenon, rust and then transported to the construction site.
(2) well-off single from column J of work, the location of the wall line and reinforced elastic good line of position.
2, material requirements
(1) steel: grade, specifications meet the design requirements. Quality meets current standards.
(2) 20 22 # fire wire, cement mortar (plastic) pads and so on.
3, equipment preparation
(1) steel cutting machine, steel bending machine, bar straightening machine, steel hook, steel wrench, wire brush, broken fire wire hay cutter and so on.
(2) ink fountain, ink, white line, chalk, etc..
(B) of the formwork
1, operating conditions
(1) part of the external walls 300mm above the template using bamboo fight