一、施工準備
(一)作業條件
裝修外用架子(高層多用吊籃或吊架)已經搭設好,并驗收合格橫豎桿及拉桿應離開墻面和窗口150—200mm,陽臺欄桿、預留孔洞及排水管處理完畢,外門窗安裝完畢,用1∶3水泥砂漿將縫隙堵塞嚴實,在外門窗為鋁合金門窗及塑鋼門窗時,為搶工期和成品保護,可以增做輔框,輔框采用鍍鋅方管,輔框內口邊和窗側旁貼完面磚平,窗比輔框上下、左右小5mm,以利于安裝,輔框固定牢固,塞堵密實,并已經檢驗合格。如先安裝完窗,要事先粘貼好保護膜,墻面基層清理干凈,腳手眼、窗臺、窗套等事先砌堵好,按面磚的尺寸、顏色進行選磚,并分類碼放好。
大面積施工前應先放大樣,并做出樣板墻,確定施工工藝及操作要點,并向施工人員做好交底工作。樣板墻完成后必須經質檢部門鑒定合格后,還要經過設計、甲方、監理和施工單位共同認定,方可組織班組按照樣板墻要求施工。
(二)材料要求First, construction preparation
(A) Operating conditions
Fitting external rack (top multi-purpose basket or hanger) has a good erection and acceptance anyway rod and bar, leave the wall and window 150-200mm, balcony railings, set aside, and drain holes disposed of, outer doors and windows installed, with 1:3 cement mortar to plug the gaps within sturdy, aluminum doors, windows and external doors and windows for the windows and doors, in order to grab the protection period and finished products can be done by secondary frame, auxiliary frame galvanized square tube, accessories and window frame mouth flat side next to the skin has tile, windows up and down than the auxiliary box, so small 5mm, to facilitate the installation of auxiliary frame fixed firmly, plug plug dense, and has been tested and qualified. Such as the first installation of windows, good protective film to advance paste, wall grassroots clean, Scaffold eyes, bay windows, window cover and other puzzle block well in advance, according to the size of tile, brick color selection and classification of laying is good.
Construction should be preceded by a large area to enlarge like, and make a model wall, construction technology and operations to determine the main points of clarification at work to do construction workers. Model after the completion of the wall must be accredited by the quality inspection department, the go through the design, Party, supervision and construction units together finds that the wall be a model organization requirements in accordance with the construction team.
(B) material requirements