④預制構件安裝
A預制混凝土構件應符合設計圖和國家標準GB50204-2002《混凝土結構工程施工及驗收規范》的規定。
B構件混凝土澆筑完畢后,應標注構件的型號和制作日期,對于上、下難以分辨的構件尚應注意“上”字,并應標注在統一的位置上。
C預制構件進場要檢查板端是否堵孔(進入板端4cm堵孔),如未堵應補堵,樓板有裂縫者,不得使用。預制構件安裝鋪放后,支座用水淋濕,再用10厚1:2.5水泥砂漿坐漿,安裝時,構件留40-60mm板縫,內附加1φ8鋼筋,縫內采用C20細石砼澆灌密實。板縫施工層不能在結構施工層進行,以避免板的變形,振動影響板縫質量。
④ Install prefabricated
A precast concrete elements should be consistent with design drawings and the national standard GB50204-2002 "Concrete Structures for construction and acceptance" requirement.
After concrete placement component B, component should be marked on the model and production date, for the upper and lower still difficult to distinguish the component should be noted that "on" and the words should be marked in a unified position.
C prefabricated panel-side approach to check whether the plug hole (hole blocking access to board-side 4cm), should be completed without blocking, block, slab cracks were not used. After laying precast installation, bearing water wet, then 10, sat thick 1:2.5 cement slurry, installation, components remain 40-60mm seams, within the additional 1φ8 steel, rock fissures using C20 thin dense shrub Tong Jiao . Construction floor slab joint construction layer in the structure can not, in order to avoid distortion of the plate, vibration seams quality.