XX鄉人民政府綜合樓施工方案.doc
進入下載頁
一、施工方案
1.1 工程概況
(1) 工程名稱:XX鄉人民政府綜合樓
(2) 工程地點:XX鄉人民政府院內
(3) 工程規模及功能分區:總建筑面積為6145m2,層數為六層,房屋高度為21.6m。各層使用功能如下:
一層∽二層:門面
三層∽六層:住宅
(4) 結構設計:基礎為振動灌注樁基礎、六層磚混、按七度抗震烈度設防,樓板除樓梯間、衛生間、廁所、客廳等為現澆板外,其余均為預應力空心板,砌體結構采用Mu10粘土磚、一至三層為M10混合砂漿、四至五層為M7.5混合砂漿、六層以上為M5混合砂漿,砼結構強度等級情況如下:
基礎采用C20砼
現澆柱、梁、板除一至三層采用C30砼外,以上均為C20砼
現澆構造柱、圈梁采用C20砼
鋼筋級別為Ⅰ、Ⅱ級。
(5) 屋面防水:剛性防水
(6) 建筑裝飾
外墻:采用外墻漆
室內地面為水泥砂漿、內墻為混合砂漿。
1.2 施工部署
1.2.1 施工管理目標
為樹立企業形象,實現各項管理目標,推行項目法管理,采用先進技術,精心組織、精心操作、優質、安全、高速、低耗建好該工程,具體目標如下:
工程質量:確保省優良工程。
施工工期:確保160天竣工交付使用。
安全生產:杜絕重大傷亡、設備、火災事故。
文明施工:執行現場標準化管理,成為文明典范。
服務目標:與各方密切配合,為設備安裝、裝修施工創造條件,使業主滿意。
1.2.2 施工組織管理機構設置
公司組建本工程項目經理部,代表公司具體對整個工程
A construction program
1.1 Project Overview
(1) Project Name: XX Township People's Government Complex Building
(2) Project Location: XX village people's government hospital
(3) The size of the project and functional area: The total construction area of 6145m2, was six storeys, housing a height of 21.6m. Layers using the following functions:
Two-story floor ∽: facade
Three ∽ six: Residential
(4) Structural design: base vibration of pile foundation, six-story brick, seven degree of seismic intensity according to fortification, except floor stairwell, bathroom, toilet, living room and so on board for the cast, the rest are prestressed hollow, clay brick masonry structure with Mu10, one to three for the M10 mixed mortar, mixing mortar four to five for the M7.5, six more than the M5 mixed mortar, concrete strength grade structure is as follows:
Using C20 concrete foundation
Cast columns, beams, plates with the exception of one to three C30 concrete, the above are concrete C20
Situ structural columns, ring beams and concrete use of C20
Steel grade for the grade Ⅰ, Ⅱ.
(5) Roofing: rigid waterproof
(6) Architectural Decoration
Wall: The outer wall paint
Indoor surface for the cement mortar, mixing mortar for the walls.
1.2 Construction of the deployment
1.2.1 Construction management objectives
To establish a corporate image, the achievement of management objectives, the implementation of the project management method, the use of advanced technology and careful organization and operation, high quality, safe, high-speed, low power built the project, specific objectives are as follows:
Quality of the project: to ensure that provincial excellent project.
Construction period: 160 days to ensure completion of delivery.
Safety: to prevent heavy casualties, equipment, and fire incidents.
Construction of civilization: the implementation of standardized management site, become a model of civilization.
Target: close cooperation with all parties for equipment installation, decoration works to create conditions for the satisfaction of the Owner.
1.2.2 Construction Management organization set
Incorporation of the Project Management Team, specifically on behalf of the company throughout the project