一、施工前控制要點(diǎn)
1、 審核承包單位的技術(shù)資質(zhì)證明文件、專業(yè)人員的資格證上崗證。
2、 審核承包單位的施工方案和施工組織設(shè)計(jì)。
3、 審核施工測(cè)量成果報(bào)驗(yàn)表、復(fù)查樁位、控制標(biāo)高等。
4、 檢查進(jìn)入現(xiàn)場(chǎng)的成品樁,接樁用電焊條等產(chǎn)品質(zhì)量及出廠技術(shù)質(zhì)量合格證書、品種、類型、規(guī)格(樁徑、管壁厚、樁長(zhǎng)強(qiáng)度、質(zhì)量(外觀應(yīng)符合設(shè)計(jì)要求和國家現(xiàn)行標(biāo)準(zhǔn)《先張法預(yù)應(yīng)力砼管樁》GB13476-92的規(guī)定及驗(yàn)收規(guī)范的規(guī)定。
5、 審查打樁設(shè)備的技術(shù)性能資料是否滿足工程實(shí)際的需要。如選擇柴油打樁錘,應(yīng)考慮如下問題:
(1) 要保證單樁承載力能達(dá)到設(shè)計(jì)要求(國內(nèi)經(jīng)驗(yàn),每個(gè)型號(hào)的柴油錘,其最大成樁能力(單樁極限承載力,約為100倍的型號(hào)數(shù)(KN),如D45型,最多可打極限承載力4500Kpa)。
(2) 要考慮樁的入土深度即樁的自重大小(憑經(jīng)驗(yàn)按錘重與樁重的比例,對(duì)一般土質(zhì)取0.5,若軟土較厚可取 0.4)。
(3) 要根據(jù)土質(zhì)、巖性和布樁狀況來選擇錘型,每根樁的總擊數(shù)宜在1500擊以內(nèi)。
(4) 要保證沖擊壓應(yīng)力不超過樁身砼極限強(qiáng)度的50%。
First, control points before construction
1, review the technical qualifications of contractors proof of professional qualification certificates work license.
2, review contractor's construction program and construction organization design.
3, audit inspection table construction survey results, review pile and control the elevation so.
4, checking into the site of the finished pile, the pile electric welding techniques such as product quality and factory quality certification, variety, type, specifications (length, diameter, pipe wall thickness, pile length and intensity, quality (appearance should be consistent with design requirements and the state the current standard of "first Prestressed Concrete Pipe" GB13476-92 requirements and acceptance requirements.
5, review the technical performance data piling equipment meets the engineering requirements. If you choose to diesel hammer, shall consider the following questions:
(1) To ensure the bearing capacity to meet the design requirements (domestic experience, each model of diesel hammer, the maximum pile capacity (single pile ultimate bearing capacity, about 100 times the model number (KN), such as the D45 type up to play ultimate capacity 4500Kpa).
(2) to consider the pile at a depth of the pile of dead weight size (rule of thumb by weight of hammer and pile weight ratio of the average soil is 0.5, if the thicker soft desirable 0.4).
(3) according to soil, rock and pile conditions to select hammer type, each pile in the 1500 general strike should hit within a few.
(4) To ensure that the impact of stress does not exceed the ultimate strength of concrete pile 50%.